References
Mining
Client: Boliden, Sweden
Project: Garpenberg Expansion
Harmonizer’s commitment:
To design reactive power compensation and harmonic filtering to meet Vattenfall’s power factor and distortion requirements.
As a result of the studies, a 10 kV and a 20 kV filter battery have been installed. Each battery consists of four filter branches tuned to the 5th, 7th, 11th and 13th harmonics switchable in 3 and 2 Mvar steps at 10 kV and 4 and 5 Mvar steps at 20 kV.
The work has consisted of the following steps.
- Power quality measurements in the existing installation
- Theoretical calculations of expected reactive power consumption and harmonic generation from the new plant
- Load flow, harmonic and transient studies for different operating cases.
- Selection of the appropriate filter configuration to meet reactive power and harmonic distortion requirements.
- Development of control scheme for reactive power control
- Preparation of rating data for filters and filter components and development of a detailed technical tender specification.
- Evaluation of tenders
- Review and approval of the supplier’s design
- Control of assembly, commissioning and verification measurements
Principal: LKAB Malmberget, Sweden
Mandate: To reduce voltage variations on 110 kV and 20 kV busbars caused by rapidly varying loads in the form of 4 40-tonne rock winches.
The scope of the work:
- Real-time measurements of power, current, voltage and harmonic variations.
- Load flow and harmonic simulations
- Selection of compensator type and power
- Evaluation of existing filters
- Development of technical specification
- Evaluation of supplier proposals
- Measurements and verification of performance and rating data after commissioning
Client: LKAB, Sweden
Mission: To analyze the cause and consequences of voltage dips in LKAB’s facilities and propose an action plan to eliminate the problems.
The scope of the work:
- Compilation and analysis of disturbance registrations at the 130 kV PCC for each LKAB site.
- Compilation and analysis of fault reports from power suppliers (Vattenfall) and LKAB.
- Summary of voltage drop related generation interruptions and corresponding loss of income
- Evaluation of possible measures for 130 kV transmission systems
- Evaluation of possible measures for distribution systems
- Evaluation of measures to improve the immunity level of production equipment
- Calculations of investment costs and payback period for the different measures
- Final recommendation and action plan
Client: LKAB, Sweden
Mission: To design compensation equipment for a new pellet plant
The scope of the work:
- Load flow study
- Harmonic study
- Selection of the appropriate filter configuration
- Calculation of rating data for filter components
- Control of assembly and verifying measurements
Aluminum smelter
Client: ABB Switzerland
Final customer: Raz Az Zawr, Saudi Arabia
- To generate 840 MVAR reactive power to improve the power factor at Point of Common Coupling (PCC).
- To filter harmonic currents generated by the rectifiers to meet the harmonic distortion requirements of IEEE Standard 519.
Scope:
- Collection of input data for the analytical model
- Choice of filter configuration
- Harmonic study
- Detailed design of filters and filter components
- Verification measurements
Client: ABB
Final customer: Raz Az Zawr, Saudi Arabia
Object: Refinery and rolling mill
- Improving the power factor at the Point of Common Coupling (PCC)
- To filter harmonic currents generated by frequency converters to meet distortion requirements according to IEEE Standard 519.
Scope:
- Collection of input data for the analytical model
- Choice of filter configuration
- Harmonic study
- Detailed design of filters and filter components
- Assembly supervision, commissioning, verification measurements
Client: ABB
Final customer: ISAAL Iceland
Scope: Design of harmonic filters for expansion projects. Total power generated 85 Mvar
The scope of the work:
- Harmonics measurements to determine existing harmonics
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet power factor and harmonic distortion requirements
- Calculation of rating data for filter components
- Control of assembly, commissioning and verification measurements
Client: ABB
Final customer: Sohar Oman
The scope of the work:
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet power factor and harmonic distortion requirements
- Calculation of rating data for filter components
Client: ABB
End customer: Nordural Island
The scope of the work:
- Harmonics measurements to map existing harmonics
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet power factor and harmonic distortion requirements
- Calculation of rating data for filter components
- Commissioning
- Verification measurements
Client: ABB
End customer: Quatalum, Qatar
The scope of the work:
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet power factor and harmonic distortion requirements
- Calculation of rating data for filter components
Distribution and transmission applications
Client: Orkuvirki, Iceland
Application: Compensation of a 130 kV substation.
Mission: To design 3 x 20 Mvar, 130 kV harmonic filters.
The scope of the work:
- Harmonics measurements on 130 kV busbars to map existing harmonics
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet harmonic distortion requirements
- Calculation of rating data for filter components
- Selection of the protection scheme and protection settings
- Control of assembly, commissioning and verification measurements
Client: ABB
End customer: PGC, Poland
Application: Reactive power compensation of three 110 kV substations.
Task: To design 3 x 50 Mvar, 110 kV harmonic filters in three different substations.
The scope of the work:
- Harmonics measurements on 110 kV and 400 kV busbars to map existing harmonics
- Harmonic study
- Transient study
- Selection of appropriate filter configuration to meet harmonic distortion requirements
- Calculation of rating data for filter components
- Selection of the protection scheme and protection settings
- Control of assembly, commissioning and verification measurements
Client: ABB
End customer: RTE, France
Application: 400 kV, 220 kV, 110 kV, 63 kV compensation projects in different locations in France.
- Harmonic analysis
- Transient study
- Calculation of rating data for filter components
- Selection of the protection scheme and protection settings
- Control of assembly, commissioning and verification measurements
Wind farms
Client: Siemens Sweden
Object: Storrotsliden Windfarm, Sweden
Scope of work::
- Power quality measurements
- EMTP modeling and transient simulations
- Diagnostics and remedies
Problem solving
Customer: Nordural, Iceland
Problem: Measuring transformer and cable failure
Harmonizer has carried out a system study consisting of on-site measurements and computer-based simulations. As a result of the study, specially designed ZnO-R-C damping circuit has been proposed and installed.
The scope of the work:
- EMTP Simulations
- Design of the damping circuit
- Procurement of components
- Commissioning
- Verification measurements.